MUSC Institute of Psychiatry Third Floor Renovation
E2 Development renovated 6,000 SF of existing lab space, and it was rehabilitated into new office spaces for the MUSC Institute of Psychiatry. The work included decommissioning existing medical gas systems, and selective demolition to accommodate the new office layout. E2 Development installed new flooring, new millwork in a kitchen and a classroom, and built out a new accessible shower.
Description
- Renovation of a 6,000 SF lab space into office spaces.
- Complied with ICRA and MUSC standards for construction and renovations.
- Modified existing walls and doors, installed new.
- Removed and decommissioned lab and medical gases.
- Provided and installed a new accessible toilet and shower room.
- Provided and installed new architectural millwork.
- HVAC Duct Cleaning
- HVAC updates to system and air devices.
- Performed pre-TAB and final TAB. Selective Demolition




Project Specifics
Role:
Prime Contractor
Client:
Medical University of South Carolina (MUSC)
Location:
67 President Street Charleston, SC 29425
Architect:
Liollio Architecture, PC